The SCR reactor adopts a fixed bed form, and the catalyst is placed in a module. The number of catalyst layers in the reactor depends on the required catalyst reaction surface area.
The typical layout is to arrange two to three catalyst layers. Above the top catalyst layer is a catalyst-free rectifying layer, which is used to ensure that the flue gas is evenly distributed when it enters the catalyst layer. Usually there is a spare space under the third catalyst layer to add the fourth catalyst layer when the catalyst activity decreases. A soot blowing device is set between the catalyst layers of the reactor, and the soot blowing and sweeping time is 30 to 120 minutes, 1 to 2 times a week.
If necessary, regular cleaning should be carried out inside the reactor. There is an ash hopper under the reactor, which is connected to the power plant ash discharge system for regular ash discharge.