News

Home/News/Details

Ghana Approves 1,200 MW State-Backed CCGT To Replace Oil-Fired Generation

Ghana's Ministry of Finance has officially announced the approval of a 1,200 MW state-owned combined-cycle gas turbine (CCGT) power plant to be built at Komenda in the Central Region, as part of the government's mid-term fiscal review. The project will be developed in two phases, with the first 600 MW phase targeting commercial operation by 2028.

 

According to the ministry's statement, the plant will be equipped with GE Vernova gas turbines and will utilize domestic and imported natural gas to replace light crude oil currently used for thermal power generation. The government estimates that switching from oil to gas will reduce generation costs by at least 75%, translating into a 10% to 20% reduction in retail electricity tariffs for consumers.